  1. If 16 men working 7 hours a day can plow a field in 48 days, in how many days will 14 men working 12 hours a day plow the same field?

  2. A.
    46
    B.
    32
    C.
    30
    D.
    35

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    Let the one-day work = number of men* total working hours per day
    Now, the ratio of total work = (14*12): (16*7)
    Now, the ratio of days = 48: x
    Where x is the required number of days
    Now, one day work is inversely proportional to the number of days:
    So, (14*12): (16*7) = 48: x
    Or, x = (48*16*7)/ (14*12) = 32
    Therefore, 32 days are required to plow the same field.