  1. A man completes  of a job in 10 days. At this rate, how many more days will it takes him to finish the job?

  2. A.

    5

    B.

    6

    C.

    7

    D.

    7\( \frac { 1 } { 2 }\)

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    Work done =\( \frac { 5 } {8 }\)

    Balance work =[1-\( \frac { 5 } {8 }\)]=\( \frac { 3 } {8 }\)

    Let the required number of days be x.

    Then,\( \frac { 5 } {8 }\):\( \frac { 3 } {8 }\)=:;10:X \( \frac { 5 } {8 }\)x =\( \frac { 3 } {8 }\)*10

     x =[\( \frac { 3 } {8 }\)*10*\( \frac {8 } {5}\)]

     x = 6.