  1. A man completes  of a job in 10 days. At this rate, how many more days will it takes him to finish the job?

  2. A.

    5

    B.

    6

    C.

    7

    D.

    712

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    Work done =58

    Balance work =[1-58]=38

    Let the required number of days be x.

    Then,58:38=:;10:X 58x =38*10

     x =[38*10*85]

     x = 6.