- A can do a piece of work in 10 days and B can do it in 15 days and C can do it 20 days. They started the work together and A leaves after 2 days and B leaves after 4 days from the beginning. How long will work lost?
Answer : Option C
Explanation :
2/10 + 4/15 + x/20 = 1
x = 32/3 = 10 2/3