Home / Arithmetic Aptitude / Time and Work :: Discussion

Discussion :: Time and Work

  1. A can do a piece of work in 10 days and B can do it in 15 days and C can do it 20 days. They started the work together and A leaves after 2 days and B leaves after 4 days from the beginning. How long will work lost?
  2. A.
    8 2/3 days
    B.
    9 2/3 days
    C.
    10 2/3 days
    D.
    10 days

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    2/10 + 4/15 + x/20 = 1

    x = 32/3 = 10 2/3


Be The First To Comment