  1. A can do a piece of work in 15 days and B in 20 days. They began the work together but 5 days before the completion of the work, A leaves. The work was completed in?
  2. A.
    8 days
    B.
    10 days
    C.
    15 days
    D.
    11 3/7 days

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    (x “ 5)/15 + x/20 = 1

    x = 11 3/7 days