Discussion :: Time and Work
- A and B can do a piece of work in 8 days. B and C can do it in 12 days and A and C in 16 days. Working together they will complete the work in how many days?
Answer : Option D
Explanation :
A + B = 1/8
B + C = 1/12
C + A = 1/16
-------------------------------
2(A + B +C) = 1/8 + 1/12 + 1/16 = 13/48
A + B +C = 13/96
96/13 = 7.38 days