  1. A can do a piece of work in 20 days. B in 15 days A and C in 12 days. In how many days can A finish the work if he is assisted by B on one day and C on the next, alternately?
  2. A.
    10
    B.
    8
    C.
    6
    D.
    4

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    A + B = 1/20 + 1/15 = 7/60

    A + C = 1/20 + 1/12 = 8/60

    7/60 + 8/60 = 15/60 = 1/4

    4 days * 2 = 8 days