Discussion :: Time and Work
- If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be?
Answer : Option A
Explanation :
Let 1 men's 1 day work = x and 1 boy's 1 day work = y.
Then, 6x + 8y = 1/10 and 26x + 48y = 1/2