  1. 12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start working on the job and after working for 2 days, all of them stopped working. How many women should be put on the job to complete the remaining work, if it so to be completed in 3 days?
  2. A.
    15
    B.
    18
    C.
    22
    D.
    Data inadequate
    E.
    None of these

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    1 man's 1 day work = 1/48; 1 woman's 1 day work = 1/60.

    6 men's 2 day's work = 6/48 * 2 = 1/4.