  1. A can complete a work in 12 days and B can complete in 8 days. A works for 8 hours every day while B works for 10 hours every day. If A and B together start working 8 hours per day, in how many days will they complete the work?
  2. A.
    8 days
    B.
    60/11 days
    C.
    39/12 days
    D.
    15/8 days

    View Answer

    Workspace

    Answer : Option B

    Explanation :