  1. A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:

  2. A.

    20days

    B.

    2212days

    C.

    25 days

    D.

    30 days

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    Ratio of times taken by A and B = 1 : 3.

     

    time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.

     

    If difference of time is 2 days, B takes .

     

    If difference of time is 60 days, B takes[3260]= 90 days.

     

    So, A takes 30 days to do the work.

     

    A's 1 day's work =130

     

    B's 1 day's work =190

     

    (A + B)'s 1 day's work =[130+190]=490=245

     

     A and B together can do the work in452=2212days.