  1. A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?

  2. A.

    23 days

    B.

    37 days

    C.

    3712

    D.

    40 days

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    Whole work is done by A in[[2054]= 25 days.

     

    Now,[1-45]i.e.,15work is done by A and B in 3 days

     

    Whole work will be done by A and B in (3 x 5) = 15 days.

     

    A's 1 day's work =125,, (A + B)'s 1 day's work =115

     

    Therefore B's 1 day's work =[115-125]=4150=275

     

    So, B alone would do the work in752=3712days