  1. P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?

  2. A.

    5\(\frac {5} {11 } \)

    B.

    5\(\frac {6} {11 } \)

    C.

    6\(\frac {5} {11 } \)

    D.

    6\(\frac {6} {11 } \)

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    P can complete the work in (12 x 8) hrs. = 96 hrs.

     

    Q can complete the work in (8 x 10) hrs. = 80 hrs.

     

     P's1 hour's work =\([ \frac { 1 } { 96 } \)+\( \frac { 1 } { 80 } ] \)=\(\frac { 11 } { 480 }\)

     

    So, both P and Q will finish the work in[\(\frac { 480 } {11 }]\)hrs

     

     Number of days of 8 hours each =\([\frac { 480 } {11 }*\)\( \frac { 1 } { 8 } \)]=\( \frac { 60} { 11}\)days=5\(\frac {5} {11 } \)days