  1. 10 women can complete a work in 7 days and 10 children take 14 days to complete the work. How many days will 5 women and 10 children take to complete the work?

  2. A.

    3

    B.

    5

    C.

    7

    D.

    Cannot be determined

    E.

    None of these

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    1 woman's 1 day's work =170

     

    1 child's 1 day's work =1140

     

    (5 women + 10 children)'s day's work =[570+10140]=[114+114]=17

     

     5 women and 10 children will complete the work in 7 days.