  1. X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?

  2. A.

    6 days

    B.

    10 days

    C.

    15 days

    D.

    20 days

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    Work done by X in 4 days =[\( \frac { 1 } { 20 } *4]\)=\( \frac { 1 } {5} \)

     

    Remaining work =[1-\( \frac { 1 } {5} \)]=\( \frac { 4 } {5} \)

     

    (X + Y)'s 1 day's work =[\( \frac { 1 } { 20 } \)+\( \frac { 1 } { 12 } \)]=\( \frac { 8} {60} \)=\( \frac { 2 } {15} \)

     

    Now,\( \frac { 2 } {15} \)work is done by X and Y in 1 day

     

    So,\( \frac { 4 } {5} \)work will be done by X and Y in[\( \frac { 15 } {2} *\)\( \frac { 4 } {5} \)]=6days

     

    Hence, total time taken = (6 + 4) days = 10 days.

     