A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?
Answer : Option B
Explanation :
Ratio of times taken by A and B = 100 : 130 = 10 : 13.
Suppose B takes x days to do the work.
Then, 10 : 13 :: 23 :
x x =\( [\frac { 23*13 } { 10}]\) x =\( \frac { 299 } {10 } \)
A's 1 day's work =\( \frac { 1 } { 23 } \)
B's 1 day's work =\(\frac { 10 } { 299 } \)
(A + B)'s 1 day's work =[\( \frac { 1 } { 23 } \)+\(\frac { 10 } { 299 } \)]=\(\frac {23 } { 299 } \)=\(\frac { 1 } { 13 }\)
Therefore, A and B together can complete the work in 13 days.