Home / Arithmetic Aptitude / Time and Work :: Discussion

Discussion :: Time and Work

  1. A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in :

  2. A.

    8 days

    B.

    10 days

    C.

    12 days

    D.

    15 days

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    (A + B)'s 1 day's work =[\( \frac { 1 } { 15} \)+\( \frac { 1 } { 10} \)]=\(\frac { 1 } {6 } \)

     

    Work done by A and B in 2 days =[\(\frac { 1 } {6 } *2]\)=\(\frac { 1 } {3 } \)

     

    Remaining work =[1-\(\frac { 1 } {3 } \)]=\(\frac { 2 } {3 } \)

     

    Now,  \(\frac { 1 } {15 } \)work is done by A in 1 day.

     

    Therefore\(\frac { 2 } {3 } \)work will be done by a in[15\( *\frac { 2 } { 3 } \)]= 10 days.

     

    Hence, the total time taken = (10 + 2) = 12 days.