  1. A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work?

  2. A.

    18 days

    B.

    24 days

    C.

    30 days

    D.

    36 days

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    2(A + B + C)'s 1 day's work =[130+124+120]=15120=18

     

    Therefore, (A + B + C)'s 1 day's work =128=116

     

    Work done by A, B, C in 10 days =1016=58

     

    Remaining work =[1-58]=38

     

    A's 1 day's work =[116-124]=148

     

    Now,148work is done by A in 1 day.

     

    So,38work will be done by A in[4838]=18days