Discussion :: Time and Work
-
A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work?
Answer : Option A
Explanation :
2(A + B + C)'s 1 day's work =[130+124+120]=15120=18
Therefore, (A + B + C)'s 1 day's work =12∗8=116
Work done by A, B, C in 10 days =1016=58
Remaining work =[1-58]=38
A's 1 day's work =[116-124]=148
Now,148work is done by A in 1 day.
So,38work will be done by A in[48∗38]=18days