A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in
Answer : Option A
Explanation :
Ratio of rates of working of A and B = 2 : 1.
So, ratio of times taken = 1 : 2.
B's 1 day's work =112
A's 1 day's work =16; (2 times of B's work)
(A + B)'s 1 day's work =[16+12]=312=14
So, A and B together can finish the work in 4 days.