Discussion :: Time and Work
-
A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in :
Answer : Option C
Explanation :
(A + B + C)'s 1 day's work =\( \frac { 1 } {6} \);
(A + B)'s 1 day's work =\( \frac { 1 } {8} \);
(B + C)'s 1 day's work =\( \frac { 1 } { 12 }\)
(A + C)'s 1 day's work=[2\(*\frac { 1 } {6 } ]\)-\([\frac { 1 } {8 }+ \)\( \frac { 1 } { 12 }]\)
=\( [\frac { 1 } { 3 } \)-\(\frac { 5 } { 24 } ]\)
=\(\frac {3 } { 24 }\)
=\( \frac { 1 } {8} \)
So, A and C together will do the work in 8 days.