Discussion :: Time and Work

  1. A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in :

  2. A.

    4 days

    B.

    6 days

    C.

    8 days

    D.

    12 days

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    (A + B + C)'s 1 day's work =16;

     

    (A + B)'s 1 day's work =18;

     

    (B + C)'s 1 day's work =112

     

    Therefore(A + C)'s 1 day's work=[216]-[18+112]

                                             =[13-524]

                                              =324

                                              =18

     

    So, A and C together will do the work in 8 days.

     