Discussion :: Time and Work

  1. A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

  2. A.

    5 days

    B.

    6 days

    C.

    10 days

    D.

    1012days

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    (B + C)'s 1 day's work =[19+112]=736

     

    Work done by B and C in 3 days =[7363]=712

     

    Remaining work =[1-712]=512

     

    Now,124work is done by A in 1 day

     

    So,512work is done by A in[24512]=10days

     