A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:
Answer : Option C
Explanation :
(B + C)'s 1 day's work =[19+112]=736
Work done by B and C in 3 days =[736∗3]=712
Remaining work =[1-712]=512
Now,124work is done by A in 1 day
So,512work is done by A in[24∗512]=10days