  1. A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?

  2. A.

    30 days

    B.

    40 days

    C.

    60 days

    D.

    70 days

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    Let A's 1 day's work = x and B's 1 day's work = y.

    Then, x + y =130and 16x + 44y = 1.

    Solving these two equations, we get: x =160and y=160

     B's 1 day's work =160

    Hence, B alone shall finish the whole work in 60 days.