Discussion :: Time and Work
-
A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in :
Answer : Option C
Explanation :
(A + B)'s 1 day's work = | 1 | + | 1 | = | 1 | . | ||
15 | 10 | 6 |
Work done by A and B in 2 days = | 1 | x 2 | = | 1 | . | ||
6 | 3 |
Remaining work = | 1 - | 1 | = | 2 | . | ||
3 | 3 |
Now, | 1 | work is done by A in 1 day. |
15 |
2 | work will be done by a in | 15 x | 2 | = 10 days. | |||
3 | 3 |
Hence, the total time taken = (10 + 2) = 12 days.
Be The First To Comment