- A can do a job in 12 days and B can do the same job in 10 days. With the help of C they can do the same job in 4 days. In how many days C alone can do this job?
Answer : Option A
Explanation :
A's one day work =
B's one day work =
(A+B+C)'s one day work =
Therefore, C's one day work = (A+B+C)'s one day work (A+B)'s one day work
So, C's one day work =
So, C will complete the work in 15 days.