- A can do a job in 30 days. B alone can do the same job in 20 days. If A starts the work and joined by B after 10 days, in how many days the job will be done?
Answer : Option D
Explanation :
A's one day work =
A's ten-day work =
So the remaining work would be =
B's one day work =
A and B's one day work =
of the job will be done by them in one day.
So, the remaining job= 8 days
Therefore, the total number of days required to do the job would be = 10 + 8 = 18 days