  1. 40 men can paint a building in 15 days working 4 hours a day. In how many days 30 men working 5 hours a day will complete the work?
  2. A.
    14 days
    B.
    15 days
    C.
    16 days
    D.
    17 days

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    Let the work will be completed in X days.

    Apply formula: M1 D1 T1 W2 = M2 D2 T2 W1

    W1=W2

    Therefore, 40 * 15 * 4 = 30 * D2 * 5

    2400 = 150 * D2

    D2 = 2400 = 16days
             150