- 3 workers can do a piece of work in 20 days. If one of them works only for half time in a day, in how many days the work will be done?
Answer : Option A
Explanation :
3 men's one day work = 1
20
One man works for half day, so his one day's work = 1 = 1
60∗2 120
Sum of each man one day's work = 1 + 1 + 1 = 5 = 1
60 60 120 120 24
Therefore, they will do the work in 24 days