Discussion :: Time and Work
- A can finish the job at the same time in which B and C together do it. If A and B together can finish the work in 10 days and C alone can do the work in 50 days, how many days B will take to complete the same job?
Answer : Option D
Explanation :
ATQ,
The efficiency of A = B+C
(A+B) can finish the work in 10 days, and C can finish the work in 50 days.
Now, A+B = 10 days
C = 50 days
Note: Assume the total work = LCM of the given days
Take the LCM of days = LCM of (10 and 50) = 50
Let the total work = 50
Note: One day work = (total work/ days)
Now,
C's one day work = 50/50 = 1
(A+B)'s one day work = 5
i.e., (A+B+C)'s one day work = 5+1=6
i.e., A+A = 6
Or, A's one day work efficiency = 3
A+B = 5, i.e., 3+B = 5
Or, B's one day efficiency=2
Hence, B alone can work in 50/2 = 25 days