  1. 30 men can complete the work in 30 days. If after every 10 days, 5 workers leave the job, the work will be finished in how many days?
  2. A.
    32 days
    B.
    35 days
    C.
    37 days
    D.
    40 days

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    Men = 30, days = 30

    Total work = men * days = 30*30 = 900 units of work

    ATQ,

    1st 10 days work done = Men * days = 30*10= 300................ (i)
    Next 10 days work done = Men * days = 25 * 10= 250.......... (ii)
    Next 10 days work done = Men * days = 20 * 10 = 200......... (iii)
    Next 10 days work done = Men * days = 15 * 10 = 150.......... (iv)

    The total work done in 40 days = 300+ 250+ 200+ 150 = 900 units

    ATQ, the total work which is 900 units should be completed in 30 days, but according to the solution, it takes 10 more days to get completed.

    So, the work will be completed in 40 days.