Home / Chemical Engineering / Chemical Engineering Plant Economics :: Discussion

Discussion :: Chemical Engineering Plant Economics

  1. If 'S' is the amount available after 'n' interest periods for an initial principal 'P' with the discrete compound interest rate 'i', the present worth is given by

  2. A.
    (1 + i)n/S
    B.
    S/(1 + i)n
    C.
    S/(1 + in)
    D.
    S/(1 + n)i

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    No answer description available for this question.


Be The First To Comment