The energy required per unit mass to grind limestone particles of very large size to 100 μm is 12.7 kWh/ton. An estimate (using Bond's law) of the energy to grind the particles from a very large size to 50 μrn is
Answer : Option C
Explanation :
No answer description available for this question.