  1. The single stage well point system of dewatering an excavation can be used if the depth of excavation does not exceed

  2. A.

     5 m

    B.

     10 m

    C.

     15 m

    D.

     20 m

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    Explanation Not Provided