  1. For a continuous slab of 3 m x 3.5 m size, the minimum overall depth of slab to satisfy vertical deflection limits is

  2. A.

     50 mm

    B.

     75 mm

    C.

     100 mm

    D.

     120 mm

    View Answer

    Workspace

    Discuss Discuss in Forum


  3. The main reinforcement in the heel of a T-shaped R.C. retaining wall is provided on

  4. A.

     top face perpendicular to wall

    B.

     bottom face perpendicular to wall

    C.

     both top and bottom faces perpendicular to wall

    D.

     none of the above

    View Answer

    Workspace

    Discuss Discuss in Forum


  5. For walls, columns and vertical faces of all structural members, the form work is generally removed after

  6. A.

     24 to 48 hours

    B.

     3 days

    C.

     7 days

    D.

     14 days

    View Answer

    Workspace

    Discuss Discuss in Forum


  7. As compared to ordinary portland cement, high alumina cement has

  8. A.

     higher initial setting time but lower final setting time

    B.

     lower initial setting time but higher final setting time

    C.

     higher initial and final setting times

    D.

     lower initial and final setting times

    View Answer

    Workspace

    Discuss Discuss in Forum


  9. The compressive strength of 100 mm cube as compared to 150 mm cube is always

  10. A.

     less

    B.

     more

    C.

     equal

    D.

     none of the above

    View Answer

    Workspace

    Discuss Discuss in Forum


  11. Approximate value of shrinkage strain in concrete, is

  12. A.

     0.003

    B.

     0.0003

    C.

     0.00003

    D.

     0.03

    View Answer

    Workspace

    Discuss Discuss in Forum


  13. A beam curved in plan is designed for

  14. A.

     bending moment and shear

    B.

     bending moment and torsion

    C.

     shear and torsion

    D.

     bending moment, shear and torsion

    View Answer

    Workspace

    Discuss Discuss in Forum


  15. The load factors for live load and dead load are taken respectively as

  16. A.

     1.5 and 2.2

    B.

     2.2 and 1.5

    C.

     1.5 and 1.5

    D.

     2.2 and 2.2

    View Answer

    Workspace

    Discuss Discuss in Forum


  17. Admixtures which cause early setting, and hardening of concrete are called

  18. A.

     workability admixtures

    B.

     accelerators

    C.

     retarders

    D.

     air entraining agents

    View Answer

    Workspace

    Discuss Discuss in Forum


  19. Ratio of permissible stress in direct compression and bending compression is

  20. A.

     less than 1

    B.

     between 1 and 1.5

    C.

     between 1.5 and 2.0

    D.

     greater than 2

    View Answer

    Workspace

    Discuss Discuss in Forum