Home / Civil Engineering / Concrete Technology :: Discussion

Discussion :: Concrete Technology

  1. For an ordinary Portland cement

  2. A.

    residual does not exceed 10% when sieved through IS Sieve No. 9

    B.

    soundness varies from 5 to 10 mm

    C.

    initial setting time is not less than 30 minutes

    D.

    compressive stress after 7 days, is not less than 175 kg/cm2

    E.

    all the above.

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    No answer description available for this question.


Be The First To Comment