  1. Under normal conditions using an ordinary cement, the period of removal of the form work, is

  2. A.

    7 days for beam soffits

    B.

    14 days for bottom slabs of spans 4.6 m and more

    C.

    21 days for bottom beams over 6 m spans

    D.

    2 days for vertical sides of columns

    E.

    all the above.

    View Answer

    Workspace

    Answer : Option E