  1.  

    While scheduling a project by C.P.M.

  2. A.

    a project is divided into various activities

    B.

    required time for each activity is established

    C.

    sequence of various activities is made according to their importance

    D.

    net work is drawn by connecting the activities and the events

    E.

    All the above.

    View Answer

    Workspace

    Discuss Discuss in Forum


  3. If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is

  4. A.

    (t1 - t2) - t

    B.

    t - (t1 - t2)

    C.

    (t1 + t2) - t

    D.

    t + (t1 - t

    View Answer

    Workspace

    Discuss Discuss in Forum


  5. Pick up the correct statement from the following:

  6. A.

    Earliest expected time is denoted by TE

    B.
    Latest occurrence time is denoted by TL
    C.

    Contractual obligation time is denoted by Ts

    D.

    Latest occurrence time is taken as contractual obligation time

    E.

    All the above.

    View Answer

    Workspace

    Discuss Discuss in Forum


  7. For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is

  8. A.

    1

    B.

    2

    C.

    3

    D.

    4

    View Answer

    Workspace

    Discuss Discuss in Forum


  9. For the execution of a project, a contractor is

  10. A.

    a person

    B.

    a firm

    C.

    an agency

    D.

    all the above.

    View Answer

    Workspace

    Discuss Discuss in Forum


  11. Railway projects are treated as

  12. A.

    light construction

    B.

    heavy construction

    C.

    industrial construction

    D.

    none of these.

    View Answer

    Workspace

    Discuss Discuss in Forum


  13. Pick up the correct statement from the following:

  14. A.

    Optimistic time estimate refers to activities

    B.

    Pessimistic time estimate refers to activities

    C.

    Most likely time estimate refers to activities

    D.

    Expected time estimate refers to activities

    E.

    All the above.

    View Answer

    Workspace

    Discuss Discuss in Forum


  15. The critical activity has

  16. A.

    maximum float

    B.

    minimum float

    C.

    zero float

    D.

    none of these.

    View Answer

    Workspace

    Discuss Discuss in Forum


  17. The main disadvantage of line organisation, is

  18. A.

    rigid structure

    B.

    extraordinary delay in communications

    C.

    Top level executions over work

    D.

    all the above.

    View Answer

    Workspace

    Discuss Discuss in Forum


  19. Pick up the correct statement from the following:

  20. A.

    The difference of latest occurence time and earliest expected time, is called slack

    B.

    The activities connecting the events having zero slack, lie on the critical path

    C.

    The critical path consumes the maximum time

    D.

    All the above.

    View Answer

    Workspace

    Discuss Discuss in Forum