Pick up the incorrect statement from the following:
A.
|
|
B.
The tail of the arrow indicates the start of the activity |
|
C.
The head of the arrow indicates the end of the activity |
|
D.
The arrows are drawn to scale from left to right |
|
E.
Each activity consumes a given time. |
Answer : Option D
Explanation :
No answer description available for this question.