  1. If totp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be

  2. A.

    \( \frac { to + 3tm+tp } { 2 } \)

    B.

    \( \frac { to + 3tm+tp } {3 } \)

    C.

    \( \frac { to + 4tm+tp } {4 } \)

    D.

    \( \frac { to + 4tm+tp } {5} \)

    E.

    \( \frac { to + 4tm+tp } {6} \)

    Answer : Option E

    Explanation :

    No answer description available for this question.