Discussion :: Construction Management
-
If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be
A.
\( \frac { to + 3tm+tp } { 2 } \) |
B.
\( \frac { to + 3tm+tp } {3 } \) |
C.
\( \frac { to + 4tm+tp } {4 } \) |
D.
\( \frac { to + 4tm+tp } {5} \) |
E.
\( \frac { to + 4tm+tp } {6} \) |
Answer : Option E
Explanation :
No answer description available for this question.