Home / Civil Engineering / Construction Management :: Discussion

Discussion :: Construction Management

  1. In the given figure, the network of a project represents

  2. A.
    activity of an excavation of a footing
    B.

    activity of an excavation which starts at event No. 1 and ends at even No. 2

    C.

    activity of excavation which takes 8 units of time

    D.

    none of these.

    Answer : Option C

    Explanation :

    No answer description available for this question.