Pick up the incorrect statement from the following:
A.
The activity is the time consuming part of a project |
|
B.
The beginning and end of a job, are called events |
|
C.
The activity which consumes maximum time, is called a node |
|
D.
|
|
E.
None of these. |
Answer : Option C
Explanation :
No answer description available for this question.