If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be
started 5 days later
completed 5 days later
performed at slower rate in 15 days
all the above.
View Answer
Workspace
Share
Copy Text
Copy URL
Answer : Option D
Explanation :
No answer description available for this question.