  1. If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

  2. A.

    started 5 days later

    B.

    completed 5 days later

    C.

    performed at slower rate in 15 days

    D.

    all the above.

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    No answer description available for this question.