  1. If TL is the latest allowable event occurrence time, total activity slack(s), is equal to

  2. A.

    LST-EST

    B.

    LFT-EFT

    C.
    TL-EFT
    D.

    all the above.

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    No answer description available for this question.