Pick up the correct statement from the following:
A.
CPM analysis is activity oriented |
B.
PERT analysis is event oriented |
C.
CPM does not make any allowance for the uncertainties in the duration of time |
D.
In CPM, the time is related to cost |
E.
All the above. |
Answer : Option E