Home / Civil Engineering / Construction Planning and Mgmt :: Discussion

Discussion :: Construction Planning and Mgmt

  1. The probability of completion of any activity within its expected time is

  2. A.

     50 %

    B.

     84.1 %

    C.

     99.9 %

    D.

     100 %

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    Explanation Not Provided