  1. For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is

  2. A.

     8 days

    B.

     9 days

    C.

     10 days

    D.

     15 days

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    Explanation Not Provided