  1. If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

  2. A.

     (a + m + b)/6

    B.

     (a + 2m + b)/6

    C.

     (a + 4m + b)/6

    D.

     (a + 5m + b)/6

    View Answer

    Workspace

    Answer : Option C

    Explanation :