  1. If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is

  2. A.

     4 days

    B.

     6 days

    C.

     10 days

    D.

     16 days

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    Explanation Not Provided