  1. For completion of a project, the critical path of the network represents

  2. A.

     Minimum time

    B.

     Maximum time

    C.

     Maximum cost

    D.

     Minimum cost

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    Explanation Not Provided