  1. Consider the following operations:
    1. Drilling
    2. Blasting
    3. Mucking
    4. Placing steel
    5. Placing concrete
    The correct sequence of these operations in tunnel construction is

  2. A.

     1, 2, 4, 3, 5

    B.

     1, 3, 2, 4, 5

    C.

     1, 2, 3, 4, 5

    D.

     1, 3, 4, 2, 5

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    Explanation Not Provided