  1. The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as

  2. A.

     Event

    B.

     Free float

    C.

     Dummy

    D.

     Constraint

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    Explanation Not Provided