- Pick up the correct reason for making conceptual (or preliminary) estimate from the following:
A.
To have a check on a definitive cost estimate |
B.
To check quotations from contractors and/or sub-contractors |
C.
To compute target estimate for the owner while drawing and specifications are in initial stage |
D.
All of these |
Answer : Option D
Explanation :
Explanation Not Provided